Yucca Mountain nuclear waste repository

Yucca Mountain
 
The proposed design

The Yucca Mountain Nuclear Waste Repository, as designated by the Nuclear Waste Policy Act amendments of 1987, is a proposed deep geological repository storage facility within Yucca Mountain for spent nuclear fuel and other high-level radioactive waste in the United States. The site is on federal land adjacent to the Nevada Test Site in Nye County, Nevada, about 80 mi (130 km) northwest of the Las Vegas Valley.

The project was approved in 2002 by the 107th United States Congress, but the 112th Congress ended federal funding for the site via amendment to the Department of Defense and Full-Year Continuing Appropriations Act, passed on April 14, 2011, during the Obama administration. The project has encountered many difficulties and was highly contested by the public, the Western Shoshone peoples, and many politicians. The project also faces strong state and regional opposition. The Government Accountability Office stated that the closure was for political, not technical or safety reasons.

This leaves the United States government (which disposes of its transuranic waste from nuclear weapons production 2,150 feet (660 m) below the surface at the Waste Isolation Pilot Plant in New Mexico) and American nuclear power plants without any designated long-term storage for their high-level radioactive waste (spent fuel) stored on-site in steel and concrete casks (dry cask storage) at 76 reactor sites in 34 states.

Under President Barack Obama, the Department of Energy (DOE) reviewed options other than Yucca Mountain for a high-level waste repository. The Blue Ribbon Commission on America's Nuclear Future, established by the Secretary of Energy, released its final report in January 2012. It detailed an urgent need to find a site suitable for constructing a consolidated geological repository, stating that any future facility should be developed by a new independent organization with direct access to the Nuclear Waste Fund, which is not subject to political and financial control as the Cabinet-level DOE is. But the site met with strong opposition in Nevada, including from then-Senate leader Harry Reid.

Under President Donald Trump, the DOE ceased deep borehole and other non–Yucca Mountain waste disposition research activities. For FY18, the DOE requested $120 million and the NRC $30 million from Congress to continue licensing activities for the Yucca Mountain Repository. For FY19, the DOE again requested $120 million but the NRC increased its request to $47.7 million. Congress decided to provide no funding for the remainder of FY18. In May 2019, Representative John Shimkus reintroduced a bill in the House for the site, but the Appropriation Committee killed an amendment by Representative Mike Simpson to add $74 million in Yucca Mountain funding to a DOE appropriations bill. On May 20, 2020, Under Secretary of Energy Mark W. Menezes testified in front of the Senate Energy and Natural Resources Committee that Trump strongly opposes proceeding with Yucca Mountain Repository.

In May 2021, Energy Secretary Jennifer Granholm said that Yucca Mountain would not be part of the Biden administration's plans for nuclear-waste disposal. She anticipated announcing the department's next steps "in the coming months".

Introduction

An infographic about the Yucca Mountain nuclear waste repository

Spent nuclear fuel is the radioactive by-product of electricity generation at commercial nuclear power plants, and high-level radioactive waste is the by-product of reprocessing spent fuel to produce fissile material for nuclear weapons. In 1982, Congress established a national policy to solve the problem of nuclear waste disposal. This policy is a federal law called the Nuclear Waste Policy Act, which made the U.S. Department of Energy (DOE) responsible for finding a site, building, and operating an underground disposal facility called a geologic repository. The recommendation to use a geologic repository dates to 1957, when the National Academy of Sciences recommended that the best way to protect the environment and public health and safety is to dispose of the waste in rock deep underground.

The DOE began studying Yucca Mountain in 1978 to determine whether it would be suitable for the nation's first long-term geologic repository for over 70,000 metric tons (69,000 long tons; 77,000 short tons) (150 million pounds) of spent nuclear fuel and high-level radioactive waste as of 2015[] stored at 121 sites around the nation. An estimated 10,000 metric tons (9,800 long tons; 11,000 short tons) of the waste would be from America's military nuclear programs.

On December 19, 1984, the DOE selected ten locations in six states for consideration as potential repository sites, based on data collected for nearly ten years. The ten sites were studied and results of these preliminary studies were reported in 1985. Based on these reports, President Ronald Reagan approved three sites for intensive scientific study called site characterization. The three sites were Hanford, Washington; Deaf Smith County, Texas; and Yucca Mountain.

In 1987, Congress amended the Nuclear Waste Policy Act and directed DOE to study only Yucca Mountain, which is adjacent to the former nuclear test site. The Act provided that if during site characterization Yucca Mountain was found unsuitable, studies would stop immediately. This option expired when Reagan actually recommended the site. On July 23, 2002, President George W. Bush signed House Joint Resolution 87, (Pub. L. 107–200 (text) (PDF)) allowing the DOE to take the next step in establishing a safe repository in which to store nuclear waste. The DOE was to begin accepting spent fuel at the Yucca Mountain Repository by January 31, 1998, but did not do so because of a series of delays due to legal challenges, concerns over how to transport nuclear waste to the facility, and political pressure resulting in underfunding of the construction.

On July 18, 2006, the DOE proposed March 31, 2017, as the date to open the facility and begin accepting waste based on full funding. On September 8, 2006, Bush nominated Ward (Edward) Sproat, a nuclear industry executive formerly of PECO energy in Pennsylvania, to lead the Yucca Mountain Project. Following the 2006 midterm congressional elections, Harry Reid, a longtime opponent of the repository, became the Senate Majority Leader, putting him in a position to greatly affect the future of the project. Reid said he would continue to work to block completion of the project, and is quoted as having said, "Yucca Mountain is dead. It'll never happen."

In the 2008 Omnibus Spending Bill, the Yucca Mountain Project's budget was reduced to $390 million. The project was able to reallocate resources and delay transportation expenditures to complete the License Application for submission on June 3, 2008. During his 2008 presidential campaign, Barack Obama promised to abandon the project. After his election, the Nuclear Regulatory Commission told Obama he did not have the ability to do so. On April 23, 2009, Lindsey Graham and eight other senators introduced legislation to provide "rebates" from a $30 billion federally managed fund into which nuclear power plants had been paying, so as to refund all collected funds if Congress canceled the project.

In November 2013, in response to a lawsuit filed by the National Association of Regulatory Utility Commissioners and the Nuclear Energy Institute, the US court of appeals ruled that nuclear utilities may stop paying into the nuclear waste recovery fund until either the DOE follows the Nuclear Waste Policy Act, which designates Yucca Mountain as the repository, or Congress changes the law. The fee ended May 16, 2014.

Lacking an operating repository, the federal government initially paid utility companies somewhere between $300 and $500 million per year in compensation for failing to comply with the contract it signed to take the spent nuclear fuel by 1998. For the ten years after 2015, it is estimated to cost taxpayers $24 billion in payments from the Judgment Fund. The Judgment Fund is not subject to budget rules and allows Congress to ignore the nuclear waste issue since payments therefrom do not have any impact on yearly spending for other programs.

Facility

A tour group entering the North Portal of Yucca Mountain

The purpose of the Yucca Mountain project is to comply with the Nuclear Waste Policy Act of 1982 and develop a national site for spent nuclear fuel and high-level radioactive waste storage. The management and operating contractor as of April 1, 2009 for the project is USA Repository Services (USA-RS), a wholly owned subsidiary of URS Corporation (now part of AECOM) with supporting principal subcontractors Shaw Corporation (now part of McDermott International Inc.) and Areva Federal Services LLC (now Orano federal services business).

After the layoff of 800 employees on March 31, 2009, about 100 employees remained on the project until all technical staff were laid off by the end of FY 2010 due to zero funding in the 2011 budget for the Office of Civilian Radioactive Waste Management. Sandia National Laboratories was responsible for post-closure analysis and ensuring compliance with the NWPA. The main tunnel of the Exploratory Studies Facility is U-shaped, 5 mi (8.0 km) long and 25 ft (7.6 m) wide.

There are also several cathedral-like alcoves that branch from the main tunnel. Most of the scientific experiments were conducted in these alcoves. The emplacement drifts (smaller-diameter tunnels branching off the main tunnel) where waste would have been stored were not constructed since they required authorization from the Nuclear Regulatory Commission. The repository has a statutory limit of 77,000 metric tons (85,000 short tons).

To store that much waste would have required 40 miles (64 km) of tunnels. The Nuclear Waste Policy Act further limits the capacity of the repository to 63,000 metric tons (62,000 long tons; 69,000 short tons) of initial heavy metal in commercial spent fuel. The 104 U.S. commercial reactors currently operating will produce this quantity of spent fuel by 2014, assuming that the spent fuel rods are not reprocessed. Currently, the US has no civil reprocessing plant.

The tunnel boring machine on display at the exit of the tunnel

By 2008, Yucca Mountain was one of the most studied pieces of geology in the world; between geologic studies and materials science, the United States had invested US$9 billion on the project. This site studied by the Nevada Bureau of Mines and Geology (NBMG) differs substantially from other potential repositories due to the finding of natural analogues of nuclear material that are currently being studied. The DOE estimates that it has over 100 million U.S. gallons of highly radioactive waste and 2,500 metric tons (2,800 short tons) of spent fuel from the production of nuclear weapons and from research activities in temporary storage.

The cost of the facility is being paid for by a combination of a tax on each kilowatt hour of nuclear power and by the taxpayers for disposal of weapons and naval nuclear waste. Based on the 2001 cost estimate, about 73% is funded by consumers of nuclear-powered electricity and 27% by the taxpayers.

The Total System Life Cycle Cost Director Sproat presented to Congress on July 15, 2008, was $90 billion. This cost could not be compared to previous estimates since it included a repository capacity about twice as large as previously estimated over a much longer period of time (100 years vs. 30 years). Additionally, the cost of the project continued to escalate because of insufficient funding to most efficiently move forward and complete the project. By 2007, the DOE announced it was seeking to double the size of the Yucca Mountain repository to a capacity of 135,000 metric tons (149,000 short tons), or 300 million pounds.

The tunnel boring machine (TBM) that excavated the main tunnel cost $13 million and was 400 ft (120 m) long when in operation. It now sits at its exit point at the South Portal (south entrance) of the facility. The short side tunnel alcoves were excavated using explosives.

Opposition

A map showing Yucca Mountain in southern Nevada, west of the Nevada Test Site

The DOE was scheduled to begin accepting spent fuel at the Yucca Mountain repository by January 31, 1998 (25 years ago). By 2010, years after this deadline, the future status of the repository at Yucca Mountain was still unknown due to ongoing litigation, and opposition by Harry Reid.

Because of construction delays, a number of nuclear power plants in the United States have resorted to dry cask storage of waste on-site indefinitely in steel and concrete casks.

The project is widely opposed in Nevada and is a hotly debated national topic. A two-thirds majority of Nevadans feel it is unfair for their state to have to store nuclear waste when there are no nuclear power plants in Nevada. Many Nevadans' opposition stemmed from the so-called "Screw Nevada Bill," the 1987 legislation halting study of Hanford and Texas as potential sites for the waste before conclusions could be made. The county containing the proposed facility, Nye County, supports the repository's development, as do six adjoining counties. A 2015 survey of Nevadans found 55% agreeing that the state should be open to discussion of what benefits could be received.

One point of concern has been the standard of radiation emission in 10,000 to 1,000,000 years. On August 9, 2005, the United States Environmental Protection Agency (EPA) proposed a limit of 350 millirem per year for that period. In October 2007, the DOE issued a draft of the Supplemental Environmental Impact Statement showing that for the first 10,000 years mean public dose would be 0.24 mrem/year and that thereafter the median public dose would be 0.98 mrem/year, both of which are substantially below the proposed EPA limit. For comparison, a hip X-ray results in a dose around 83 mrem and a CT head or chest scan results in around 1,110 mrem. Annually, in the United States, an individual's dose from background radiation is about 350 mrem, though some places get more than twice that.

On February 12, 2002, Secretary of Energy Spencer Abraham decided that this site was suitable to be the nation's nuclear repository. The governor of Nevada had 90 days to object and did so, but Congress overrode the objection. If the governor's objection had stood, the project would have been abandoned and a new site chosen. In August 2004, the repository became an election issue when Senator John Kerry said he would abandon the plans if elected.

In March 2005, the Energy and Interior departments revealed that several U.S. Geological Survey hydrologists had exchanged emails discussing possible falsification of quality assurance documents on water infiltration research. On February 17, 2006, the DOE's Office of Civilian Radioactive Waste Management (OCRWM) released a report confirming the technical soundness of infiltration modeling work performed by U.S. Geological Survey (USGS) employees. In March 2006, the U.S. Senate Committee on Environment and Public Works Majority Staff issued a 25-page white paper, "Yucca Mountain: The Most Studied Real Estate on the Planet." The conclusions were:

  • Extensive studies consistently show Yucca Mountain to be a sound site for nuclear waste disposal;
  • The cost of not moving forward is extremely high;
  • Nuclear waste disposal capability is an environmental imperative;
  • Nuclear waste disposal capability supports national security;
  • Demand for new nuclear plants also demands disposal capability.

On January 18, 2006, DOE OCRWM announced that it would designate Sandia National Laboratories as its lead laboratory to integrate repository science work for the Yucca Mountain Project. "We believe that establishing Sandia as our lead laboratory is an important step in our new path forward. The independent, expert review that the scientists at Sandia will perform will help ensure that the technical and scientific basis for the Yucca Mountain repository is without question," OCRWM's Acting Director Paul Golan said. "Sandia has unique experience in managing scientific investigations in support of a federally licensed geologic disposal facility, having served in that role as the scientific advisor to the Waste Isolation Pilot Plant in Carlsbad, New Mexico." Sandia began acting as the lead laboratory on October 1, 2006.

Because of questions raised by the State of Nevada and congressional members about the quality of the science behind Yucca Mountain, the DOE announced on March 31, 2006, the selection of Oak Ridge Associated Universities/Oak Ridge Institute for Science and Education (a not-for-profit consortium that includes 96 doctoral degree-granting institutions and 11 associate member universities) to provide expert reviews of scientific and technical work on the Yucca Mountain Project. DOE stated that the project "will be based on sound science. By bringing in Oak Ridge for review of technical work, DOE will seek to present a high level of expertise and credibility as they move the project forward ... This award gives DOE access to academic and research institutions to help DOE meet their mission and legal obligation to license, construct, and open Yucca Mountain as the nation's repository for spent nuclear fuel."

There was significant public and political opposition to the project in Nevada. An attempt was made to push ahead with it and override the opposition. But for large projects that would take decades to complete, there is every chance that sustained local opposition will prevail, and this happened with the Yucca Mountain project. Successful nuclear waste storage siting efforts in Scandinavia have involved local communities in the decision-making process and given them a veto at each stage, but this did not happen with Yucca Mountain. Local communities at potential storage and repository sites "should have early and continued involvement in the process, including funding that would allow them to retain technical experts".

On March 5, 2009, Energy Secretary Steven Chu reiterated in a Senate hearing that the Yucca Mountain site was no longer considered an option for storing reactor waste.

On March 3, 2010, the DOE filed a motion with the NRC to withdraw its license application, but multiple lawsuits to stop this action have been filed by states, counties, and individuals across the country as being unauthorized by the NWPA.

The costly nuclear accident in 2014 at New Mexico's Waste Isolation Pilot Plant in which a nuclear waste container exploded has caused doubt that it could serve as an alternative for Yucca.

In January 2019, Governor Steve Silolak vowed that "not one ounce" of nuclear waste would be allowed at Yucca Mountain, and a May funding bill did not include funding for the site. In May 2019, the Reno Gazette-Journal published a long-form essay cataloging opposition to the Yucca Mountain project. According to a tribal elder, the Western Shoshone view Yucca Mountain as sacred and a nuclear storage facility "will poison everything. It's people's life, our Mother Earth's life, all the living things here, all the creatures; whatever's crawling around, it's their life too." The tribes say they lack funds to discredit federal safety claims, but will be directly affected by a potential disaster.

Radiation standards

A tunnel inside the Exploratory Studies Facility.

Original standard

The EPA established its Yucca Mountain standards in June 2001. The storage standard set a dose limit of 15 millirem per year for the public outside the Yucca Mountain site. The disposal standards consisted of three components: an individual dose standard, a standard evaluating the impacts of human intrusion into the repository, and a groundwater protection standard. The individual-protection and human intrusion standards set a limit of 15 millirem per year to a reasonably maximally exposed individual, who would be among the most highly exposed members of the public.

The groundwater protection standard is consistent with EPA's Safe Drinking Water Act standards, which the Agency applies in many situations as a pollution prevention measure. The disposal standards were to apply for 10,000 years after the facility is closed. Dose assessments were to continue beyond 10,000 years and be placed in DOE's Environmental Impact Statement, but were not subject to a compliance standard.

The 10,000-year period for compliance assessment is consistent with EPA's generally applicable standards developed under the Nuclear Waste Policy Act. It also reflects international guidance regarding the level of confidence that can be placed in numerical projections over very long periods of time.

Inconsistent standards

Shortly after the EPA first established these standards in 2001, the nuclear industry, several environmental and public interest groups, and the State of Nevada challenged the standards in court. In July 2004, the Court of Appeals for the District of Columbia Circuit found in favor of the Agency on all counts except one: the 10,000 year regulatory time frame. The court ruled that EPA's 10,000-year compliance period for isolation of radioactive waste was not consistent with National Academy of Sciences (NAS) recommendations and was too short.

The NAS report had recommended standards be set for the time of peak risk, which might approach a period of one million years. By limiting the compliance time to 10,000 years, EPA did not respect a statutory requirement that it develop standards consistent with NAS recommendations.

EPA's rule

EPA published in the Federal Register a final rule in 2009. The new rule limits radiation doses from Yucca Mountain for up to 1,000,000 years after it closes. Within that regulatory time frame, the EPA has two dose standards that would apply based on the number of years from the time the facility is closed.

For the first 10,000 years, the EPA would retain the 2001 final rule's dose limit of 15 millirem per year. This is protection at the level of the most stringent radiation regulations in the U.S. today. From 10,000 to one million years, EPA established a dose limit of 100 millirem per year. EPA's rule requires DOE to show that Yucca Mountain can safely contain wastes, considering the effects of earthquakes, volcanic activity, climate change, and container corrosion, over one million years. The current analysis indicates that the repository will cause less than 1 mrem/year public dose for 1,000,000 years.

Geology

Looking west atop Yucca Mountain

The formation that makes up Yucca Mountain was created by several large eruptions from a caldera volcano and is composed of alternating layers of ignimbrite (welded tuff), non-welded tuff, and semi-welded tuff. The tuff surrounding the burial sites is expected to protect human health as it provides a natural barrier to the radiation. It lies along the transition between the Mojave and the Great Basin Deserts.

The volcanic tuff at Yucca Mountain is appreciably fractured and movement of water through an aquifer below the waste repository is primarily through fractures. While the fractures are usually confined to individual layers of tuff, the faults extend from the planned storage area all the way to the water table 600 to 1,500 ft (180 to 460 m) below the surface. Future water transport from the surface to waste containers is likely to be dominated by fractures. There is evidence that surface water has been transported down through the 700 ft (210 m) of overburden to the exploratory tunnel at Yucca Mountain in less than 50 years.

The aquifer of Yucca Mountain drains to Amargosa Valley, home to over 1400 people and a number of endangered species.

Some site opponents assert that, after the predicted containment failure of the waste containers, these cracks may provide a route for movement of radioactive waste that dissolves in the water flowing downward from the desert surface. Officials state that the waste containers will be stored in such a way as to minimize or even nearly eliminate this possibility.

The area around Yucca Mountain received much more rain in the geologic past and the water table was consequently much higher than it is today, though well below the level of the repository.

Earthquakes

DOE has stated that seismic and tectonic effects on the natural systems at Yucca Mountain will not significantly affect repository performance. Yucca Mountain lies in a region of ongoing tectonic deformation, but the deformation rates are too slow to significantly affect the mountain during the 10,000-year regulatory compliance period. Rises in the water table caused by seismic activity would be, at most, a few tens of meters and would not reach the repository. The fractured and faulted volcanic tuff that Yucca Mountain comprises reflects the occurrence of many earthquake-faulting and strong ground motion events during the last several million years, and the hydrological characteristics of the rock would not be changed significantly by seismic events that may occur in the next 10,000 years. The engineered barrier system components will reportedly provide substantial protection of the waste from seepage water, even under severe seismic loading.

In September 2007, it was discovered that the Bow Ridge fault line ran underneath the facility, hundreds of feet east of where it was originally thought to be located, beneath a storage pad where spent radioactive fuel canisters would be cooled before being sealed in a maze of tunnels. The discovery required several structures to be moved several hundred feet further to the east, and drew criticism from Robert R. Loux, then head of the Nevada Agency for Nuclear Projects, who argues that Yucca administrators should have known about the fault line's location years prior, and called the movement of the structures "just-in-time engineering."

In June 2008, a major nuclear equipment supplier, Holtec International, criticized DOE's safety plan for handling containers of radioactive waste before they are buried at the proposed Yucca Mountain dump. The concern is that, in an earthquake, the unanchored casks of nuclear waste material awaiting burial at Yucca Mountain could be sent into a "chaotic melee of bouncing and rolling juggernauts".

Transportation of waste

The nuclear waste was planned to be shipped to the site by rail and/or truck in robust containers known as spent nuclear fuel shipping casks, approved by the Nuclear Regulatory Commission. While the routes in Nevada would have been public, in the other states the planned routes, dates and times of transport would have been secret for security reasons. State and tribal representatives would have been notified before shipments of spent nuclear fuel entered their jurisdictions.

Nevada routes

The proposed Transportation Route of spent nuclear fuel through Nevada

Within Nevada, the planned primary mode of transportation was via rail through the Caliente Corridor. This corridor starts in Caliente, Nevada, traveling along the northern and western borders of the Nevada Test Site for approximately 200 miles (320 km). At this point, it turns south.

Other options that were being considered included a rail route along the Mina corridor. This rail route would have originated at the Fort Churchill Siding rail line, near Wabuska. The proposed corridor would have proceeded southeast through Hawthorne, Blair Junction, Lida Junction and Oasis Valley. At Oasis Valley, the rail line would have turned north-northeast towards Yucca Mountain. Use of this rail corridor by DOE would have required permission from the Walker River Paiute Tribe in order to cross their land. As the first 54 miles (87 km) of the proposed corridor was owned by the Department of Defense (DoD), additional permission from the DoD would have to have been granted.

The Nevada Center for Biological Diversity and the Nevada Attorney General both have expressed concern about the transportation routes, "through any number of sensitive habitats."

Impacts

Since the early 1960s, the U.S. has safely conducted more than 3,000 shipments of spent nuclear fuel without any harmful release of radioactive material. This safety record is comparable to the worldwide experience where more than 70,000 metric tons of spent nuclear fuel have been transported since 1970 – an amount approximately equal to the total amount of spent nuclear fuel that would have been shipped to Yucca Mountain.

But cities were still concerned about the transport of radioactive waste on highways and railroads that may have passed through heavily populated areas. Dr. Robert Halstead, a transportation adviser to the state of Nevada since 1988, said of transportation of the high-level waste, "They would heavily affect cities like Buffalo, Cleveland, Pittsburgh, in the Chicago metropolitan area, in Omaha." "Coming out of the south, the heaviest impacts would be in Atlanta, in Nashville, St. Louis, Kansas City, moving across through Salt Lake City, through downtown Las Vegas, up to Yucca Mountain. And the same cities would be affected by rail shipments as well." Spencer Abraham (DOE) said, "I think there's a general understanding that we move hazardous materials in this country, an understanding that the federal government knows how to do it safely."

In October 2018, a state senator from Utah argued that transferring nuclear waste from other states to Yucca Mountain on state highways and railways could be a health hazard.

Cultural impact

Archaeological surveys have found evidence that Native Americans used the immediate vicinity of Yucca Mountain on a temporary or seasonal basis. Some Native Americans disagree with the conclusions of archaeological investigators that their ancestors were highly mobile groups of hunter-gatherers who occupied the Yucca Mountain area before Euroamericans began using the area for prospecting, surveying, and ranching. They believe that these conclusions overlook traditional accounts of farming that occurred before European contact.

Yucca Mountain and surrounding lands were central in the lives of the Southern Paiute, Western Shoshone, and Owens Valley Paiute and Shoshone peoples, who shared them for religious ceremonies, resource uses, and social events.

Delays since 2009

Starting in 2009, the Obama administration attempted to close the Yucca Mountain repository, despite current US law that designates Yucca Mountain as the nation's nuclear waste repository. The administration agency, DOE, began implementation of the President's plan in May 2009. The Nuclear Regulatory Commission also went along with the administration's closure plan. Various state and congressional entities attempted to challenge the administration's closure plans, by statute and in court.

Most recently, in August 2013, a US Court of Appeals decision told the NRC and the Obama administration that they must either "approve or reject [DOE's] application for [the] never-completed waste storage site at Nevada's Yucca Mountain." They cannot simply make plans for its closure in violation of US law.

In May 2009, then United States Secretary of Energy Steven Chu stated:

Yucca Mountain as a repository is off the table. What we're going to be doing is saying, let's step back. We realize that we know a lot more today than we did 25 or 30 years ago. The NRC is saying that the dry cask storage at current sites would be safe for many decades, so that gives us time to figure out what we should do for a long-term strategy. We will be assembling a blue-ribbon panel to look at the issue. We're looking at reactors that have a high-energy neutron spectrum that can actually allow you to burn down the long-lived actinide waste. These are fast-neutron reactors. There's others: a resurgence of hybrid solutions of fusion fission where the fusion would impart not only energy, but again creates high-energy neutrons that can burn down the long-lived actinides. ...

Some of the waste is already vitrified. There is, in my mind, no economical reason why you would ever think of pulling it back into a potential fuel cycle. So one could well imagine—again, it depends on what the blue-ribbon panel says—one could well imagine that for a certain classification for a certain type of waste, you don't want to have access to it anymore, so that means you could use different sites than Yucca Mountain, such as salt domes. Once you put it in there, the salt oozes around it. These are geologically stable for a 50 to 100 million year time scale. The trouble with those type of places for repositories is you don't have access to it anymore. But say for certain types of waste you don't want to have access to it anymore—that's good. It's a very natural containment. ... whereas there would be other waste where you say it has some inherent value, let's keep it around for a hundred years, two hundred years, because there's a high likelihood we'll come back to it and want to recover that.

So the real thing is, let's get some really wise heads together and figure out how you want to deal with the interim and long-term storage. Yucca was supposed to be everything to everybody, and I think, knowing what we know today, there's going to have to be several regional areas.

In 2008, the U.S. Senate Committee on Environmental and Public Works found that failure to perform to contractual requirements could cost taxpayers up to $11 billion by 2020. In 2013, this estimate of taxpayer liability was raised to $21 billion. In July 2009, the House of Representatives voted 388 to 30 on amendments to HHR3183 (Roll call vote 591, via Clerk.House.gov) to not defund the Yucca Mountain repository in the FY2010 budget. In 2013, the House of Representatives voted twice during the 2014 Energy and Water Appropriations debate by over 80% majority to reject elimination of Yucca Mountain as the nation's only nuclear waste solution.

On April 13, 2010, the state of Washington filed suit to prevent the closing of Yucca Mountain, since this would slow efforts to clean up Hanford Nuclear Reservation. South Carolina, Aiken County (the location of Savannah River site) and others joined Washington. The United States Court of Appeals for the District of Columbia Circuit dismissed the suit in July 2011, saying the Nuclear Regulatory Commission had not ruled on the withdrawal of the license application. Washington and South Carolina filed another lawsuit on July 29.

With $32 billion received from power companies to fund the project, and $12 billion spent to study and build it, the federal government had $27 billion left, including interest. In March 2012, Senator Lindsey Graham introduced a bill requiring three-fourths of that money to be given back to customers, and the remainder to the companies for storage improvements.

In August 2013, the U.S. Court of Appeals for the District of Columbia ordered the Nuclear Regulatory Commission to either "approve or reject [DOE's] application for [the] never-completed waste storage site at Nevada's Yucca Mountain." The court opinion said that the NRC was "simply flouting the law" in its previous action to allow the Obama administration to continue plans to close the proposed waste site since a federal law designating Yucca Mountain as the nation's nuclear waste repository remains in effect. The court opinion stated that "The president may not decline to follow a statutory mandate or prohibition simply because of policy objections."

In response, NRC issued the final volumes of the Yucca Mountain Safety Evaluation Report (SER), which included the NRC staff's statement that the site would meet all applicable standards. At the same time, the staff also stated that NRC should not authorize construction of the repository until the requirements for land and water rights were met and a supplement to DOE's environmental impact statement (EIS) was finished. On March 3, 2015, NRC ordered the staff to complete the supplemental EIS and make the Yucca Mountain licensing document database publicly available, using all the remaining previously appropriated licensing funds.

In March 2015, Senator Lamar Alexander introduced the Nuclear Waste Administration Act of 2015 (S854) in the U.S. Senate. It was intended to establish a fully independent Nuclear Waste Administration (NWA) that would develop nuclear waste storage and disposal facilities. Construction of such facilities would require the consent of the state, local, and tribal governments that may be affected. The NWA would be required to complete a mission plan to open a pilot storage facility by 2021 for nuclear waste from non-operating reactors and other "emergency" deliveries (called "priority waste").

The goal would be to have a storage facility for waste from operating reactors or other "non-priority waste" available by 2025, and an actual permanent repository by the end of 2048. The current disposal limit of 70,000 metric tons for the nation's initial permanent repository would be repealed. Any nuclear waste fees collected after S854 was enacted would be held in a newly established Working Capital Fund. The Nuclear Waste Administration would be allowed to draw from that fund any amounts needed to carry out S.854, unless limited by annual appropriations or authorizations. S854 died in committee.

As of September 30, 2021, the Nuclear Waste Fund had an investment fair value of $52.4 billion.

Related legislation (2017–2019)

On March 15, 2017, the Trump administration announced it would request congressional approval for $120 million to restart licensing activity at the Yucca Mountain repository, with funding also to be used to create an interim storage program. The project would consolidate nuclear waste across the United States in Yucca Mountain, which had been stockpiled in local locations since 2010. The federal budget proposal was refused by Senate. Although his administration had allocated money to the project, in October 2018, President Donald Trump stated he opposed the use of Yucca mountain for dumping, saying he agreed "with the people of Nevada."

On May 11, 2018, the bill H.R. 3053 was approved in a 340–72 vote in the House of Representatives. The bill directed the DOE to resume the licensing process for Yucca Mountain, with licensing for a permanent site at the mountain to "take up to five years." The Nuclear Waste Policy Amendments Act was sponsored by John Shimkus. The Hill clarified that the bill would "set a path forward for the DOE to resume the process of planning for and building the southern Nevada site, transfer land to the DOE for it, ease the federal funding mechanism and allow DOE to build or license a temporary site to store waste while the Yucca project is being planned and built."

The bill would "direct [DOE] to revive the licensing process for Yucca Mountain to be designated as the country’s permanent site for nuclear waste." The bill would bring together waste from 121 locations in 39 states. All Nevada representatives opposed the bill. The measure was scheduled to go to the Senate next, and if passed there, would require the Nuclear Regulatory Commission to decide on the matter within 30 months.

The Hill noted that the bill received widespread support from lawmakers arguing that nuclear waste was best transferred out of their districts to Yucca, a concept opposed by Nevada representatives, with politicians such as Dina Titus dubbing it the "Screw Nevada 2.0" bill. Titus proposed an amendment that would have required long-term storage to be kept in locales that consented, which the House rejected, 332–80. In their opposition to the use of Yucca Mountain as a nuclear repository, Nevada representatives were supported by Dianne Feinstein of California and other politicians.

In June 2018, the Trump administration and some members of Congress again began proposing using Yucca Mountain, with Nevada Senators raising opposition. By early 2019, use of Yucca Mountain was in "political limbo" as opposition to the site led to an impasse. In January 2019, a panel of scientists introduced to Congress a 126-page report, Reset of America’s Nuclear Waste Management, which proposed including Yucca Mountain as a potential repository with "development of a consensus-based siting process, but one that would still include Yucca Mountain as a candidate."

Nevada National Security Site officials in April 2019 assured the public that the Device Assembly Facility on the Nevada security site was safe from earthquake threats. In contrast, Nevada officials claimed seismic activity in the region made it unsafe for the storage of nuclear waste. On April 1, 2019, the Las Vegas Review-Journal noted that "Nevada Democrats in the House" were seeking to block transfers of plutonium from DOE into the state by the use of the appropriations process.

Saturday, August 5, 2023

Mars landing

From Wikipedia, the free encyclopedia
Animation of a Mars landing touchdown, the InSight lander in 2018

A Mars landing is a landing of a spacecraft on the surface of Mars. Of multiple attempted Mars landings by robotic, uncrewed spacecraft, ten have had successful soft landings. There have also been studies for a possible human mission to Mars, including a landing, but none have been attempted. Soviet Union’s Mars 3, which landed in 1971, was the first successful Mars landing. As of 2023, the Soviet Union, United States, and China have conducted Mars landings successfully.

Methods of descent and landing

As of 2021, all methods of landing on Mars have used an aeroshell and parachute sequence for Mars atmospheric entry and descent, but after the parachute is detached, there are three options. A stationary lander can drop from the parachute back shell and ride retrorockets all the way down, but a rover cannot be burdened with rockets that serve no purpose after touchdown.

One method for lighter rovers is to enclose the rover in a tetrahedral structure which in turn is enclosed in airbags. After the aeroshell drops off, the tetrahedron is lowered clear of the parachute back shell on a tether so that the airbags can inflate. Retrorockets on the back shell can slow descent. When it nears the ground, the tetrahedron is released to drop to the ground, using the airbags as shock absorbers. When it has come to rest, the tetrahedron opens to expose the rover.

If a rover is too heavy to use airbags, the retrorockets can be mounted on a sky crane. The sky crane drops from the parachute back shell and, as it nears the ground, the rover is lowered on a tether. When the rover touches ground, it cuts the tether so that the sky crane (with its rockets still firing) will crash well away from the rover.

Descent of heavier payloads

The thrusters of the InSight lander dug pits during landing beneath it at its landing site.

For landers that are even heavier than the Curiosity rover (which required a 4.5 meter (15 feet) diameter aeroshell), engineers are developing a combination rigid-inflatable Low-Density Supersonic Decelerator that could be 8 meters (28 feet) in diameter. It would have to be accompanied by a proportionately larger parachute.

Landing challenges

Landing robotic spacecraft, and possibly some day humans, on Mars is a technological challenge. For a favorable landing, the lander module has to address these issues:

In 2018, NASA successfully landed the InSight lander on the surface of Mars, re-using Viking-era technology. But this technology cannot afford the ability to land large number of cargoes, habitats, ascent vehicles and humans in case of crewed Mars missions in near future. In order to improve and accomplish this intent, there is need to upgrade technologies and launch vehicles. For a successive soft-landing using current technology, some of the considerable factors for a lander such as:

Communicating with Earth

Beginning with the Viking program, all landers on the surface of Mars have used orbiting spacecraft as communications satellites for relaying their data to Earth. The landers use UHF transmitters to send their data to the orbiters, which then relay the data to Earth using either X band or Ka band frequencies. These higher frequencies, along with more powerful transmitters and larger antennas, permit the orbiters to send the data much faster than the landers could manage transmitting directly to Earth, which conserves valuable time on the receiving antennas.

List of Mars landings

Insight Mars lander view in December 2018

In the 1970s, several USSR probes unsuccessfully tried to land on Mars. Mars 3 landed successfully in 1971 but failed shortly thereafter. The American Viking landers however made it to the surface and provided several years of images and data. However, there was not another successful Mars landing until 1997, when Mars Pathfinder landed. In the 21st century there have been several successful landings, but there have also been many crashes.

Mars probe program

The first probe intended to be a Mars impact lander was the Soviet Mars 1962B, unsuccessfully launched in 1962.

In 1970 the Soviet Union began the design of Mars 4NM and Mars 5NM missions with super-heavy uncrewed Martian spacecraft. First was Marsokhod, with a planned date of early 1973, and second was the Mars sample return mission planned for 1975. Both spacecraft were intended to be launched on the N1 rocket, but this rocket never flew successfully and the Mars 4NM and Mars 5NM projects were cancelled.

In 1971 the Soviet Union sent probes Mars 2 and Mars 3, each carrying a lander, as part of the Mars probe program M-71. The Mars 2 lander failed to land and impacted Mars. The Mars 3 lander became the first probe to successfully soft-land on Mars, but its data-gathering had less success. The lander began transmitting to the Mars 3 orbiter 90 seconds after landing, but after 14.5 seconds, transmission ceased for unknown reasons. The cause of the failure may have been related to the extremely powerful Martian dust storm taking place at the time. These space probes each contained a Mars rover although they were never deployed.

In 1973, the Soviet Union sent two more landers to Mars, Mars 6 and Mars 7. The Mars 6 lander transmitted data during descent but failed upon impact. The Mars 7 probe separated prematurely from the carrying vehicle due to a problem in the operation of one of the onboard systems (attitude control or retro-rockets) and missed the planet by 1,300 km (810 mi).

The double-launching Mars 5M (Mars-79) sample return mission was planned for 1979, but was cancelled due to complexity and technical problems.

Viking program

Viking 1 landing site (click image for detailed description).

In 1976 two American Viking probes entered orbit about Mars and each released a lander module that made a successful soft landing on the planet's surface. They subsequently had the first successful transmission of large volumes of data, including the first color pictures and extensive scientific information. Measured temperatures at the landing sites ranged from 150 to 250 K (−123 to −23 °C; −190 to −10 °F), with a variation over a given day of 35 to 50 °C (95 to 122 °F). Seasonal dust storms, pressure changes, and movement of atmospheric gases between the polar caps were observed. A biology experiment produced possible evidence of life, but it was not corroborated by other on-board experiments.

While searching for a suitable landing spot for Viking 2's lander, the Viking 1 orbiter photographed the landform that constitutes the so-called "Face on Mars" on 25 July 1976.

The Viking program was a descendant of the cancelled Voyager program, whose name was later reused for a pair of outer solar system probes.

Mars Pathfinder

"Ares Vallis" as photographed by Mars Pathfinder

NASA's Mars Pathfinder spacecraft, with assistance from the Mars Global Surveyor orbiter, landed on 4 July 1997. Its landing site was an ancient flood plain in Mars' northern hemisphere called Ares Vallis, which is among the rockiest parts of Mars. It carried a tiny remote-controlled rover called Sojourner, the first successful Mars rover, that traveled a few meters around the landing site, exploring the conditions and sampling rocks around it. Newspapers around the world carried images of the lander dispatching the rover to explore the surface of Mars in a way never achieved before.

Until the final data transmission on 27 September 1997, Mars Pathfinder returned 16,500 images from the lander and 550 images from the rover, as well as more than 15 chemical analyses of rocks and soil and extensive data on winds and other weather factors. Findings from the investigations carried out by scientific instruments on both the lander and the rover suggest that in the past Mars has been warm and wet, with liquid water and a thicker atmosphere. The mission website was the most heavily trafficked up to that time.

Spate of failures

Conceptual drawing of the Mars Polar Lander on the surface of Mars.
Mars Spacecraft 1988–1999
Spacecraft Evaluation Had or was Lander
Phobos 1 No For Phobos
Phobos 2 Yes For Phobos
Mars Observer No No
Mars 96 No Yes
Mars Pathfinder Yes Yes
Mars Global Surveyor Yes No
Mars Climate Orbiter No No
Mars Polar Lander No Yes
Deep Space 2 No Yes
Nozomi No No

Mars 96, an orbiter launched on 16 November 1996 by Russia, failed when the planned second burn of the Block D-2 fourth stage did not occur. Following the success of Global Surveyor and Pathfinder, another spate of failures occurred in 1998 and 1999, with the Japanese Nozomi orbiter and NASA's Mars Climate Orbiter, Mars Polar Lander, and Deep Space 2 penetrators all suffering various terminal errors. Mars Climate Orbiter is infamous for Lockheed Martin engineers mixing up the usage of U.S. customary units with metric units, causing the orbiter to burn up while entering Mars's atmosphere. Out of 5–6 NASA missions in the 1990s, only 2 worked: Mars Pathfinder and Mars Global Surveyor, making Mars Pathfinder and its rover the only successful Mars landing in the 1990s.

Mars Express and Beagle 2

On 2 June 2003, the European Space Agency's Mars Express set off from Baikonur Cosmodrome to Mars. The Mars Express craft consisted of the Mars Express Orbiter and the lander Beagle 2. Although the landing probe was not designed to move, it carried a digging device and the least massive spectrometer created to date, as well as a range of other devices, on a robotic arm in order to accurately analyse soil beneath the dusty surface.

The orbiter entered Mars orbit on 25 December 2003, and Beagle 2 should have entered Mars' atmosphere the same day. However, attempts to contact the lander failed. Communications attempts continued throughout January, but Beagle 2 was declared lost in mid-February, and a joint inquiry was launched by the UK and ESA that blamed principal investigator Colin Pillinger's poor project management. Nevertheless, Mars Express Orbiter confirmed the presence of water ice and carbon dioxide ice at the planet's south pole. NASA had previously confirmed their presence at the north pole of Mars.

Signs of the Beagle 2 lander were found in 2013 by the HiRISE camera on NASA's Mars Reconnaissance Orbiter, and the Beagle 2's presence was confirmed in January 2015, several months after Pillinger's death. The lander appears to have successfully landed but not deployed all of its power and communications panels.

Mars Exploration Rovers

Shortly after the launch of Mars Express, NASA sent a pair of twin rovers toward the planet as part of the Mars Exploration Rover mission. On 10 June 2003, NASA's MER-A (Spirit) Mars Exploration Rover was launched. It successfully landed in Gusev Crater (believed once to have been a crater lake) on 3 January 2004. It examined rock and soil for evidence of the area's history of water. On 7 July 2003, a second rover, MER-B (Opportunity) was launched. It landed on 24 January 2004 in Meridiani Planum (where there are large deposits of hematite, indicating the presence of past water) to carry out similar geological work.

Despite a temporary loss of communication with the Spirit rover (caused by a file system anomaly) delaying exploration for several days, both rovers eventually began exploring their landing sites. The rover Opportunity landed in a particularly interesting spot, a crater with bedrock outcroppings. In fast succession, mission team members announced on 2 March that data returned from the rover showed that these rocks were once "drenched in water", and on 23 March that it was concluded that they were laid down underwater in a salty sea. This represented the first strong direct evidence for liquid water on Mars at some time in the past.

Towards the end of July 2005, it was reported by the Sunday Times that the rovers may have carried the bacteria Bacillus safensis to Mars. According to one NASA microbiologist, this bacteria could survive both the trip and conditions on Mars. Despite efforts to sterilise both landers, neither could be assured to be completely sterile.

Having been designed for only three-month missions, both rovers lasted much longer than planned. Spirit lost contact with Earth in March 2010, 74 months after commencing exploration. Opportunity, however, continued to carry out surveys of the planet, surpassing 45 km (28 mi) on its odometer by the time communication with it was lost in June 2018, 173 months after it began. These rovers have discovered many new things, including Heat Shield Rock, the first meteorite to be discovered on another planet.

Here is some debris from a Mars landing, as viewed by a Rover. This shows the area around a heat shield and resulting shield impact crater. The heat shield was jettisoned during the descent, impacting the surface on its own trajectory, while the spacecraft went on to land the rover.

Phoenix

Camera on Mars orbiter snaps Phoenix suspended from its parachute during descent through Mars' atmosphere.

Phoenix launched on 4 August 2007, and touched down on the northern polar region of Mars on 25 May 2008. It is famous for having been successfully photographed while landing, since this was the first time one spacecraft captured the landing of another spacecraft onto a planet.

Mars Science Laboratory

Mars Science Laboratory (and the Curiosity rover) descending on Mars

The Mars Science Laboratory (MSL) (and Curiosity rover), launched in November 2011, landed in a location that is now called "Bradbury Landing", on Aeolis Palus, between Peace Vallis and Aeolis Mons ("Mount Sharp"), in Gale Crater on Mars on 6 August 2012, 05:17 UTC. The landing site was in Quad 51 ("Yellowknife") of Aeolis Palus near the base of Aeolis Mons. The landing site was less than 2.4 km (1.5 mi) from the center of the rover's planned target site after a 563,000,000 km (350,000,000 mi) journey. NASA named the landing site "Bradbury Landing", in honor of author Ray Bradbury, on 22 August 2012.

ExoMars Schiaparelli

Model of Schiaparelli lander at ESOC

The Schiaparelli lander was intended to test technology for future soft landings on the surface of Mars as part of the ExoMars project. It was built in Italy by the European Space Agency (ESA) and Roscosmos. It was launched together with the ExoMars Trace Gas Orbiter (TGO) on 14 March 2016 and attempted a landing on 19 October 2016. Telemetry was lost about one minute before the scheduled landing time, but confirmed that most elements of the landing plan, including heat shield operation, parachute deployment, and rocket activation, had been successful. The Mars Reconnaissance Orbiter later captured imagery showing what appears to be Schiaparelli's crash site.

InSight

Phoenix landing art, similar to Insight

NASA's InSight lander, designed to study seismology and heat flow from the deep interior of Mars, was launched on 5 May 2018. It landed successfully in Mars's Elysium Planitia on 26 November 2018.

Mars 2020 and Tianwen-1

NASA's Mars 2020 and CNSA's Tianwen-1 were both launched in the July 2020 window. Mars 2020's rover Perseverance successfully landed, in a location that is now called "Octavia E. Butler Landing", in Jezero Crater on 18 February 2021, Ingenuity helicopter was deployed and took subsequent flights in April. Tianwen-1's lander and Zhurong rover landed in Utopia Planitia on 14 May 2021 with the rover being deployed on 22 May, 2021 and dropping a remote selfie camera on 1 June, 2021.

Future missions

The ESA Rosalind Franklin is planned for launch in the late 2020s and would obtain soil samples from up to 2 metres (6 ft 7 in) depth and make an extensive search for biosignatures and biomolecules. There is also a proposal for a Mars Sample Return Mission by ESA and NASA, which would launch in 2024 or later. This mission would be part of the European Aurora Programme.

The Indian Space Research Organisation (ISRO) has proposed to include landing of a rover in its third Mars mission around 2030 near Eridania basin.

Landing site identification

As a Mars lander approaches the surface, identifying a safe landing spot is a concern.

The inset frames show how the lander's descent imaging system is identifying hazards (NASA, 1990)
Mars Landing Sites (16 December 2020]
Map of Mars
Interactive image map of the global topography of Mars, overlaid with the position of Martian rovers and landers. Coloring of the base map indicates relative elevations of Martian surface.
Clickable image: Clicking on the labels will open a new article.
Legend:   Active (white lined, ※)  Inactive  Planned (dash lined, ⁂)
Bradbury Landing
Deep Space 2
Mars Polar Lander
Perseverance
Schiaparelli EDM
Spirit
Viking 1
Map of MarsAcheron FossaeAcidalia PlanitiaAlba MonsAmazonis PlanitiaAonia PlanitiaArabia TerraArcadia PlanitiaArgentea PlanumArgyre PlanitiaChryse PlanitiaClaritas FossaeCydonia MensaeDaedalia PlanumElysium MonsElysium PlanitiaGale craterHadriaca PateraHellas MontesHellas PlanitiaHesperia PlanumHolden craterIcaria PlanumIsidis PlanitiaJezero craterLomonosov craterLucus PlanumLycus SulciLyot craterLunae PlanumMalea PlanumMaraldi craterMareotis FossaeMareotis TempeMargaritifer TerraMie craterMilankovič craterNepenthes MensaeNereidum MontesNilosyrtis MensaeNoachis TerraOlympica FossaeOlympus MonsPlanum AustralePromethei TerraProtonilus MensaeSirenumSisyphi PlanumSolis PlanumSyria PlanumTantalus FossaeTempe TerraTerra CimmeriaTerra SabaeaTerra SirenumTharsis MontesTractus CatenaTyrrhen TerraUlysses PateraUranius PateraUtopia PlanitiaValles MarinerisVastitas BorealisXanthe Terra
The image above contains clickable links

Interactive image map of the global topography of Mars, overlain with locations of Mars Memorial sites. Hover your mouse over the image to see the names of over 60 prominent geographic features, and click to link to them. Coloring of the base map indicates relative elevations, based on data from the Mars Orbiter Laser Altimeter on NASA's Mars Global Surveyor. Whites and browns indicate the highest elevations (+12 to +8 km); followed by pinks and reds (+8 to +3 km); yellow is 0 km; greens and blues are lower elevations (down to −8 km). Axes are latitude and longitude; Polar regions are noted.

Three-body problem

From Wikipedia, the free encyclopedia https://en.wikipedia.org/wiki/Three-body_problem Approximate tra...