Search This Blog

Thursday, August 5, 2021

Martian meteorite

From Wikipedia, the free encyclopedia

Martian meteorite (SNC meteorites)

EETA79001 S80-37631.jpg
Martian meteorite EETA79001, shergottite
TypeAchondrite
Subgroups
Parent bodyMars
Total known specimens277 as of 15 September 2020
MarsMeteorite-NWA7034-716969main black beauty full.jpg
Martian meteorite NWA 7034, nicknamed "Black Beauty," weighs approximately 320 g (11 oz).

A Martian meteorite is a rock that formed on Mars, was ejected from the planet by an impact event, and traversed interplanetary space before landing on Earth as a meteorite. As of September 2020, 277 meteorites had been classified as Martian, less than half a percent of the 72,000 meteorites that have been classified.

There are three groups of Martian meteorite: shergottites, nakhlites and chassignites, collectively known as SNC meteorites. Several other Martian meteorites are ungrouped.

These meteorites are interpreted as Martian because they have elemental and isotopic compositions that are similar to rocks and atmospheric gases on Mars, which have been measured by orbiting spacecraft, surface landers and rovers. The term does not include meteorites found on Mars, such as Heat Shield Rock.

History

By the early 1980s, it was obvious that the SNC group of meteorites (Shergottites, Nakhlites, Chassignites) were significantly different from most other meteorite types. Among these differences were younger formation ages, a different oxygen isotopic composition, the presence of aqueous weathering products, and some similarity in chemical composition to analyses of the Martian surface rocks in 1976 by the Viking landers. Several scientists suggested these characteristics implied the origin of SNC meteorites from a relatively large parent body, possibly Mars. Then in 1983, various trapped gases were reported in impact-formed glass of the EET79001 shergottite, gases which closely resembled those in the Martian atmosphere as analyzed by Viking. These trapped gases provided direct evidence for a Martian origin. In 2000, an article by Treiman, Gleason and Bogard gave a survey of all the arguments used to conclude the SNC meteorites (of which 14 had been found at the time) were from Mars. They wrote, "There seems little likelihood that the SNCs are not from Mars. If they were from another planetary body, it would have to be substantially identical to Mars as it now is understood."

Subdivision

The Martian meteorites are divided into three groups (orange) and two grouplets (yellow). SHE = Shergottite, NAK = Nakhlite, CHA = Chassignite, OPX = Orthopyroxenite (ALH 84001), BBR = Basaltic Breccia (NWA 7034).

As of April 25, 2018, 192 of the 207 Martian meteorites are divided into three rare groups of achondritic (stony) meteorites: shergottites (169), nakhlites (20), chassignites (3), and ones otherwise (15) (containing the orthopyroxenite (OPX) Allan Hills 84001, as well as 10 basaltic breccia meteorites). Consequently, Martian meteorites as a whole are sometimes referred to as the SNC group. They have isotope ratios that are said to be consistent with each other and inconsistent with the Earth. The names derive from the location of where the first meteorite of their type was discovered.

Shergottites

Roughly three-quarters of all Martian meteorites can be classified as shergottites. They are named after the Shergotty meteorite, which fell at Sherghati, India in 1865. Shergottites are igneous rocks of mafic to ultramafic lithology. They fall into three main groups, the basaltic, olivine-phyric (such as the Tissint group found in Morocco in 2011) and Lherzolitic shergottites, based on their crystal size and mineral content. They can be categorised alternatively into three or four groups based on their rare-earth element content. These two classification systems do not line up with each other, hinting at complex relationships between the various source rocks and magmas from which the shergottites formed.

NWA 6963, a shergottite found in Morocco, September 2011.

The shergottites appear to have crystallised as recently as 180 million years ago, which is a surprisingly young age considering how ancient the majority of the surface of Mars appears to be, and the small size of Mars itself. Because of this, some have advocated the idea that the shergottites are much older than this. This "Shergottite Age Paradox" remains unsolved and is still an area of active research and debate.

The 3-million-year-old crater Mojave, 58.5 km in diameter and the youngest crater of its size on the planet, has been identified as a potential source of these meteorites.

Nakhlites

Nakhla meteorite's two sides and its inner surfaces after breaking it

Nakhlites are named after the first of them, the Nakhla meteorite, which fell in El-Nakhla, Alexandria, Egypt in 1911 and had an estimated weight of 10 kg.

Nakhlites are igneous rocks that are rich in augite and were formed from basaltic magma from at least four eruptions, spanning around 90 million years, from 1416 ± 7 to 1322 ± 10 million years ago. They contain augite and olivine crystals. Their crystallization ages, compared to a crater count chronology of different regions on Mars, suggest the nakhlites formed on the large volcanic construct of either Tharsis, Elysium, or Syrtis Major Planum.

It has been shown that the nakhlites were suffused with liquid water around 620 million years ago and that they were ejected from Mars around 10.75 million years ago by an asteroid impact. They fell to Earth within the last 10,000 years.

Chassignites

The first chassignite, the Chassigny meteorite, fell at Chassigny, Haute-Marne, France in 1815. There has been only one other chassignite recovered, named Northwest Africa (NWA) 2737. NWA 2737 was found in Morocco or Western Sahara in August 2000 by meteorite hunters Bruno Fectay and Carine Bidaut, who gave it the temporary name "Diderot." It was shown by Beck et al. that its "mineralogy, major and trace element chemistry as well as oxygen isotopes revealed an unambiguous Martian origin and strong affinities with Chassigny."

Ungrouped meteorites

Allan Hills 84001 (ALH 84001)

Among these, the famous specimen Allan Hills 84001 has a different rock type from other Martian meteorites: it is an orthopyroxenite (an igneous rock dominantly composed of orthopyroxene). For this reason it is classified within its own group, the "OPX Martian meteorites". This meteorite received much attention after an electron microscope revealed structures that were considered to be the fossilized remains of bacteria-like lifeforms. As of 2005, scientific consensus was that the microfossils were not indicative of Martian life, but of contamination by earthly biofilms. ALH 84001 is as old as the basaltic and intermediate shergottite groups – i.e., 4.1 billion years old.

In March 2004 it was suggested that the unique Kaidun meteorite, which landed in Yemen on December 3, 1980, may have originated on the Martian moon of Phobos. Because Phobos has similarities to C-type asteroids and because the Kaidun meteorite is a carbonaceous chondrite, Kaidun is not a Martian meteorite in the strict sense. However, it may contain small fragments of material from the Martian surface.

The Martian meteorite NWA 7034 (nicknamed "Black Beauty"), found in the Sahara desert during 2011, has ten times the water content of other Mars meteorites found on Earth. The meteorite contains components as old as 4.42 ± 0.07 Ga (billion years), and was heated during the Amazonian geologic period on Mars.

Origin

The majority of SNC meteorites are quite young compared to most other meteorites and seem to imply that volcanic activity was present on Mars only a few hundred million years ago. The young formation ages of Martian meteorites was one of the early recognized characteristics that suggested their origin from a planetary body such as Mars. Among Martian meteorites, only ALH 84001 and NWA 7034 have radiometric ages older than about 1400 Ma (Ma = million years). All nakhlites, as well as Chassigny and NWA 2737, give similar if not identical formation ages around 1300 Ma, as determined by various radiometric dating techniques. Formation ages determined for many shergottites are variable and much younger, mostly ~150-575 Ma. The chronological history of shergottites is not totally understood, and a few scientists have suggested that some may actually have formed prior to the times given by their radiometric ages, a suggestion not accepted by most scientists. Formation ages of SNC meteorites are often linked to their cosmic-ray exposure (CRE) ages, as measured from the nuclear products of interactions of the meteorite in space with energetic cosmic ray particles. Thus, all measured nakhlites give essentially identical CRE ages of approximately 11 Ma, which when combined with their possible identical formation ages indicates ejection of nakhlites into space from a single location on Mars by a single impact event. Some of the shergottites also seem to form distinct groups according to their CRE ages and formation ages, again indicating ejection of several different shergottites from Mars by a single impact. However, CRE ages of shergottites vary considerably (~0.5–19 Ma), and several impact events are required to eject all the known shergottites. It had been asserted that there are no large young craters on Mars that are candidates as sources for the Martian meteorites, but subsequent studies claimed to have a likely source for ALH 84001 and a possible source for other shergottites.

In a 2014 paper, several researchers claimed that all shergottites meteorites come from the Mojave Crater on Mars.

Age estimates based on cosmic ray exposure

A Martian meteorite crafted into a small pendant and suspended from a silver necklace.

The amount of time spent in transit from Mars to Earth can be estimated by measurements of the effect of cosmic radiation on the meteorites, particularly on isotope ratios of noble gases. The meteorites cluster in families that seem to correspond to distinct impact events on Mars.

It is thought, therefore, that the meteorites all originate in relatively few impacts every few million years on Mars. The impactors would be kilometers in diameter and the craters they form on Mars tens of kilometers in diameter. Models of impacts on Mars are consistent with these findings.

Ages since impact determined so far include

Type Age (mya)
Dhofar 019, olivine-phyric shergottite 19.8 ± 2.3
ALH 84001, orthopyroxenite 15.0 ± 0.8
Dunite (Chassigny) 11.1 ± 1.6
Six nakhlites 10.8 ± 0.8
Lherzolites 3.8–4.7
Six basaltic shergottites 2.4–3.0
Five olivine-phyric shergottites 1.2 ± 0.1
EET 79001 0.73 ± 0.15

Possible evidence of life

Several Martian meteorites have been found to contain what some think is evidence for fossilized Martian life forms. The most significant of these is a meteorite found in the Allan Hills of Antarctica (ALH 84001). Ejection from Mars seems to have taken place about 16 million years ago. Arrival on Earth was about 13 000 years ago. Cracks in the rock appear to have filled with carbonate materials (implying groundwater was present) between 4 and 3.6 billion-years-ago. Evidence of polycyclic aromatic hydrocarbons (PAHs) have been identified with the levels increasing away from the surface. Other Antarctic meteorites do not contain PAHs. Earthly contamination should presumably be highest at the surface. Several minerals in the crack fill are deposited in phases, specifically, iron deposited as magnetite, that are claimed to be typical of biodepositation on Earth. There are also small ovoid and tubular structures that might be nanobacteria fossils in carbonate material in crack fills (investigators McKay, Gibson, Thomas-Keprta, Zare). Micropaleontologist Schopf, who described several important terrestrial bacterial assemblages, examined ALH 84001 and opined that the structures are too small to be Earthly bacteria and don't look especially like lifeforms to him. The size of the objects is consistent with Earthly "nanobacteria", but the existence of nanobacteria itself is controversial.

Many studies disputed the validity of the fossils. For example, it was found that most of the organic matter in the meteorite was of terrestrial origin. But, a recent study suggests that magnetite in the meteorite could have been produced by Martian microbes. The study, published in the journal of the Geochemical and Meteoritic Society, used more advanced high resolution electron microscopy than was possible in 1996. A serious difficulty with the claims for a biogenic origin of the magnetites is that the majority of them exhibit topotactic crystallographic relationships with the host carbonates (i.e., there are 3D orientation relationships between the magnetite and carbonate lattices), which is strongly indicative that the magnetites have grown in-situ by a physico-chemical mechanism.

While water is no indication of life, many of the meteorites found on Earth have shown water, including NWA 7034 which formed during the Amazonian period of Martian geological history. Other signs of surface liquid water on Mars (such as recurring slope lineae) are a topic of debate among planetary scientists, but generally consistent with the earlier evidence provided by martian meteorites. Any liquid water present is likely too minimal to support life.

 

Wednesday, August 4, 2021

Space Launch System

From Wikipedia, the free encyclopedia

Space Launch System
Sls block1 on-pad sunrisesmall.jpg
An artist's rendering of SLS Block 1 with Orion spacecraft on the pad before launch.
FunctionSuper heavy-lift launch vehicle
Country of originUnited States
Project costUS$18.6 billion (as of 2020)
Cost per launchOver US$2 billion excluding development (estimate)
Cost per yearUS$2.5 billion for 2020
Size
Height111.25 m (365.0 ft), Block 2 Cargo
Diameter8.4 m (28 ft), core stage
Stages2
Capacity
Payload to LEO
Mass
  • Block 1: 95 t (209,000 lb) 
  • Block 2: 130 t (290,000 lb) 
Payload to trans-lunar injection
Mass
  • Block 1: > 27 t (60,000 lb)
  • Block 1B Crew: 38 t (83,700 lb)
  • Block 1B Cargo: 42 t (92,500 lb)
  • Block 2 Crew: > 43 t (94,700 lb)
  • Block 2 Cargo: > 46 t (101,400 lb)
Associated rockets
Comparable
Launch history
StatusActive
Launch sitesKennedy Space Center, LC-39B
First flightNET 22 November 2021
Notable payloadsArtemis 1, Orion

Boosters (Block 1, 1B)
No. boosters2 five-segment Solid Rocket Boosters
Length54 m (177 ft) 
Gross mass730 t (1,610,000 lb) 
Thrust14.6 MN (1,490 tf; 3,300,000 lbf) sea level
16 MN (1,600 tf; 3,600,000 lbf) vacuum
Total thrust29.2 MN (2,980 tf; 6,600,000 lbf) sea level
32 MN (3,300 tf; 7,200,000 lbf) vacuum 
Specific impulse269 s (2.64 km/s)
Burn time126 seconds
PropellantPBAN, APCP
First stage (Block 1, 1B, 2) – Core stage
Length65 m (212 ft) 
Diameter8.4 m (27.6 ft)
Empty mass85 t (187,990 lb)
Gross mass979 t (2,159,322 lb)
Engines4 RS-25D/E 
Thrust9.1 MN (930 tf) vacuum
Specific impulse366 s (3.59 km/s) (sea level)
452 s (4.43 km/s)
Burn time480 seconds
PropellantLH2 / LOX
Second stage (Block 1) – ICPS
Length13.7 m (45 ft)
Diameter5 m (16 ft)
Empty mass3.5 t (7,690 lb)
Gross mass30.7 t (67,700 lb)
Engines1 RL10B-2
Thrust110.1 kN (11.23 tf; 24,800 lbf)
Specific impulse465.5 s (4.565 km/s)
Burn time1125 seconds
PropellantLH2 / LOX
Second stage (Block 1B, Block 2) – Exploration Upper Stage
Length17.6 m (58 ft)
Diameter8.4 m (28 ft)
Engines4 RL10C-3, later 4 RL10C-X
Thrust440 kN (45 tf; 99,000 lbf)
PropellantLH2 / LOX

The Space Launch System (SLS) is an American super heavy-lift expendable launch vehicle, which has been under development by NASA since its announcement in 2011. It replaced the Ares I, Ares V, and Jupiter planned launch vehicles, which all never left the development phase. Like those proposals, it is a design derived from the components and technology of the earlier Space Shuttle.

It had been planned to become the primary launch vehicle of NASA's deep space exploration plans throughout the 2010s (now 2020s), including the planned crewed lunar flights of the Artemis program and a possible follow-on human mission to Mars. SLS is intended to replace the retired Space Shuttle as NASA's flagship vehicle. Following the cancellation of the Constellation program, the NASA Authorization Act of 2010 envisioned a single launch vehicle usable for both crew and cargo. In 2013, SLS was projected to be the most capable super-heavy lift launch vehicle ever built.

The initial variant of SLS, Block 1, was required by the U.S. Congress to lift a payload of 70 t (69 long tons; 77 short tons) to low Earth orbit (LEO), but it was later planned to exceed that requirement with a rated payload capacity of 95 t (93 long tons; 105 short tons). As of 22 December 2019, this variant is planned to launch Artemis 1, Artemis 2, and Artemis 3. The later Block 1B is intended to debut the Exploration Upper Stage and launch the notional Artemis 4 through Artemis 7. Block 2 is planned to replace the initial Shuttle-derived boosters with advanced boosters and would have a LEO capability of more than 130 t (130 long tons; 140 short tons), again as required by Congress. Block 2 is intended to enable crewed launches to Mars.

As of 2018, SLS was planned to have the world's highest-ever total LEO payload capability, but not the world's highest ever injection mass. The SLS is planned to launch the Orion spacecraft and use the ground operations and launch facilities at NASA's Kennedy Space Center in Florida. The rocket will use the Launch Complex 39B at the Kennedy Space Center. The first launch is currently scheduled for 4 November 2021.

Vehicle description

The SLS is a Space Shuttle-derived launch vehicle, with the first stage of the rocket being powered by one central core stage and two outboard boosters. The upper stage is being developed from the Block 1 variant to a Block 1B and 2 variant, the Exploration Upper Stage.

Core stage

The Space Launch System's core stage contains the Main Propulsion System (MPS) of the launch vehicle. It is 65 m (212 ft) long by 8.4 m (27.6 ft) in diameter and fuels the four RS-25 rocket engines at its base. The core stage is structurally and visually similar to the Space Shuttle external tank, containing the liquid hydrogen fuel and liquid oxygen oxidizer. Flights 1 through 4 are planned to use modified RS-25D engines left over from the Space Shuttle program. However, the RS-25 engines were designed with reuse in mind for the Space Shuttle, so later flights are planned to switch to a expendable optimized RS-25 variant, lowering per engine costs over 30%.

The core stage is fabricated at NASA's Michoud Assembly Facility and is common across all currently planned evolutions of the SLS to avoid the need for redesigns to meet varying requirements.

Boosters

SLS Booster test at Orbital ATK/Northrop Grumman's desert facility northwest of Ogden, Utah, March 2015

Block 1 and 1B boosters

Blocks 1 and 1B of the SLS are planned to use two five-segment Solid Rocket Boosters (SRBs). These new SRBs are derived from the four-segment Space Shuttle Solid Rocket Boosters, with the addition of a center booster segment, new avionics, and lighter insulation. The five-segment SRBs provide approximately 25% more total impulse than the Shuttle SRB, but will no longer be recovered after use.

Booster Obsolescence and Life Extension program

The stock of SLS boosters is limited by the number of casings left over from the Shuttle program, since they modify flown boosters to add an additional segment. There are enough to last through eight flights of the SLS, but a replacement will be required for further flights. On 2 March 2019, the Booster Obsolescence and Life Extension (BOLE) program was announced. This program will use new solid rocket boosters built by Northrop Grumman Innovation Systems for further SLS flights. These boosters would be derived from the composite-casing SRBs in development for the OmegA launch vehicle before it was canceled, and are projected to increase Block 1B's payload to TLI by 3–4 metric tons, which is still 1 ton below the payload capacity of Block 2.

Block 2 – advanced boosters

Block 2 will have special advanced boosters which will enable Block 2 to carry 130 metric tons (130 long tons; 140 short tons) to LEO and at least 46 metric tons (45 long tons; 51 short tons) to TLI.

Upper stage

ICPS – Block 1

The Interim Cryogenic Propulsion Stage (ICPS) is planned to fly on Artemis 1. It is a stretched and human-rated Delta IV 5-meter (16 ft) Delta Cryogenic Second Stage (DCSS) powered by a single RL10B-2 engine. Block 1 is intended to be capable of lifting 95 tonnes to low Earth orbit (LEO) in this configuration if the ICPS is considered part of the payload. Artemis 1 is to be launched into an initial 1,800 by −93 km (1,118 by −58 mi) suborbital trajectory to ensure safe disposal of the core stage. ICPS will then perform an orbital insertion burn at apogee and a subsequent translunar injection burn to send Orion towards the Moon. The ICPS for Artemis 1 was delivered by ULA to NASA about July 2017, and was housed at Kennedy Space Centre as of November 2018. As of February 2020, ICPS (not EUS) is planned for Artemis 1, 2, and 3. ICPS will be human-rated for the crewed Artemis 2 flight.

EUS – Block 1B and 2

The Exploration Upper Stage (EUS) is planned to fly on Artemis 4. Similar to the S-IVB, the EUS will complete the SLS ascent phase and then re-ignite to send its payload to destinations beyond LEO. It is expected to be used by Block 1B and Block 2, share the core stage diameter of 8.4 meters, and be powered by four RL10C-3 engines. It will eventually be upgraded to use four RL10C-X engines instead.

Payload carrying capacity

Resilience

The SLS is planned to have the ability to tolerate 23 tanking cycles, 13 are reserved for launch attempts on Artemis 1. The assembled rocket is to be able to remain at the launch pad for at least 180 days and can remain in a stacked configuration for at least 200 days.

Development history

Diagram of four versions of the Space Launch System rocket
Planned evolution of the Space Launch System, 2018

Program history

During the joint Senate-NASA presentation in September 2011, it was stated that the SLS program had a projected development cost of US$18 billion through 2017, with US$10 billion for the SLS rocket, US$6 billion for the Orion spacecraft and US$2 billion for upgrades to the launch pad and other facilities at Kennedy Space Center. These costs and schedule were considered optimistic in an independent 2011 cost assessment report by Booz Allen Hamilton for NASA.

An internal 2011 NASA document estimated the cost of the program through 2025 to total at least $41 billion for four 95-tonne launches (1 uncrewed, 3 crewed), with the 130-tonne version ready no earlier than 2030.

The Human Exploration Framework Team (HEFT) estimated unit costs for Block 0 at US$1.6 billion and Block 1 at US$1.86 billion in 2010. However, since these estimates were made the Block 0 SLS vehicle was dropped in late 2011, and the design was not completed.

In September 2012, an SLS deputy project manager stated that US$500 million per launch is a reasonable target cost for SLS.

In 2013, the Space Review estimated the cost per launch at US$5 billion, depending on the rate of launches. NASA announced in 2013 that the European Space Agency (ESA) will build the Orion service module.

In 2011, NASA announced an "Advanced Booster Competition", to be decided in 2015, which would select whose boosters would be used for Block 2 of the SLS.

Several companies proposed boosters for this competition:

  • Aerojet, in partnership with Teledyne Brown, offered a booster powered by three new AJ1E6 LOX/RP-1 oxidizer-rich staged combustion engines, each producing 4,900 kN (1,100,000 lbf) thrust using a single turbopump to supply dual combustion chambers. On 14 February 2013, Aerojet was awarded a US$23.3 million, 30-month contract to build a 2,400 kN (550,000 lbf) main injector and thrust chamber.
  • Alliant Techsystems (ATK) proposed an advanced SRB nicknamed "Dark Knight", which would switch to a lighter composite case, use a more energetic propellant, and reduce the number of segments from five to four.

In 2013, the manager of NASA's SLS advanced development office indicated that all three approaches were viable.

However, this competition was planned for a development plan in which Block 1A would be followed by Block 2A, with upgraded boosters. NASA canceled Block 1A and the planned competition in April 2014. Due to this cancellation, it was reported in February 2015 that SLS is expected to fly with the original five-segment SRB until at least the late 2020s. This decision was vindicated as a later study found that the advanced booster would have resulted in unsuitably high acceleration. The overly powerful booster would need modifications to Launch Pad 39B (LC-39B), its flame trench, and Mobile Launcher, which are being evaluated.

In August 2014, as the SLS program passed its Key Decision Point C review and entered full development, costs from February 2014 until its planned launch in September 2018 were estimated at US$7.021 billion. Ground systems modifications and construction would require an additional US$1.8 billion over the same time period.

In October 2018, NASA's inspector general reported that the Boeing core stage contract had made up 40% of the US$11.9 billion spent on SLS as of August 2018. By 2021, core stages were expected to have cost a total of US$8.9 billion, which is twice the initially planned amount.

In December 2018, NASA estimated that yearly budgets for SLS will range from US$2.1 to US$2.3 billion between 2019 and 2023.

In March 2019, the Trump Administration released its Fiscal Year 2020 Budget Request for NASA. This budget did not include any money for the Block 1B and Block 2 variants of SLS. It was therefore uncertain whether these future variants of SLS will be developed, but congressional action restored this funding in the passed budget. Several launches previously planned for the SLS Block 1B are now expected to fly on commercial launcher vehicles such as Falcon Heavy, New Glenn and Vulcan. However, the request for a budget increase of US$1.6 billion towards SLS, Orion, and crewed landers along with the launch manifest seem to indicate support of the development of Block 1B, debuting Artemis 3. The Block 1B will be used mainly for co-manifested crew transfers and logistical needs rather than constructing the Gateway. An uncrewed Block 1B is planned to launch the Lunar Surface Asset in 2028, the first lunar outpost of the Artemis program. Block 2 development will most likely start in the late 2020s after NASA is regularly visiting the lunar surface and shifts focus towards Mars.

Blue Origin submitted a proposal to replace the Exploration Upper Stage with an alternative to be designed and fabricated by the company, but it was rejected by NASA in November 2019 on multiple grounds. These included lower performance compared to the existing EUS design, unsuitability of the proposal to current ground infrastructure, and unacceptable acceleration in regards to Orion components.

On March 18th 2021, CS-1 successfully completed its 8 minute Green Run test.

Funding history

For fiscal years 2011 through 2020, the SLS program had expended funding totaling US$18.648 billion in nominal dollars. This is equivalent to US$20.314 billion in 2020 dollars using the NASA New Start Inflation Indices.

For fiscal year 2021, US$2.257 billion.

Fiscal year Funding (millions) Status
Nominal In US$2020
2011 US$1,536.1 US$1,819.9 Actual
(Formal SLS Program reporting excludes the Fiscal 2011 budget.)
2012 US$1,497.5 US$1,755.5 Actual
2013 US$1,414.9 US$1,634.1 Actual
2014 US$1,600.0 US$1,812.3 Actual
2015 US$1,678.6 US$1,863.8 Actual
2016 US$1,971.9 US$2,159.6 Actual
2017 US$2,127.1 US$2,286.8 Actual
2018 US$2,150.0 US$2,256.6 Actual
2019 US$2,144.0 US$2,199.9 Actual
2020 US$2,525.8 US$2,525.8 Enacted
2021 US$2,585.9 US$2,585.9 Enacted
2011–2020 Total: US$18,648 Total: US$20,314

On top of this, the costs to assemble, integrate, prepare and launch the SLS and its payloads are funded separately under Exploration Ground Systems, currently about US$600 million per year.

Excluded from the above SLS costs are:

  • Costs of payloads for the SLS (such as Orion crew capsule)
  • Costs of the predecessor Ares V / Cargo Launch Vehicle (funded from 2008 to 2010)
  • Costs for the Ares I / Crew Launch Vehicle (funded from 2006 to 2010, a total of US$4.8 billion in development that included the 5-segment Solid Rocket Boosters that will be used on the SLS)

Included in the above SLS costs are:

  • Costs of the interim Upper Stage for the SLS, the Interim Cryogenic Propulsion Stage (ICPS) for SLS, which includes a US$412 million contract 
  • Costs of the future Upper Stage for the SLS, the Exploration Upper Stage (EUS) (funded at US$85 million in 2016, US$300 million in 2017, US$300 million in 2018, and US$150 million in 2019)

Per launch costs

The per launch costs for SLS have varied widely, partly due to uncertainty over how much the program will expend during development and testing before the operational launches begin, and partly due to various agencies using differing cost measures (for example, a marginal cost per one additional launch, which ignores development and annual recurring fixed costs vs. total cost per launch, including recurring costs but excluding development); but also based on differing purposes for which the cost estimates were developed.

There are no official NASA estimates for how much SLS will cost per launch, nor for the SLS program annual recurring costs once operational. Cost per launch is not a straightforward figure to estimate as it depends heavily on how many launches occur per year. For example, similarly, the Space Shuttle was estimated (in 2012 dollars) to cost US$576 million per launch had it been able to achieve 7 launches per year, while the marginal cost of adding a single additional launch in a given year was estimated to be less than half of that, at just US$252 million of marginal cost. However, at the rate that it actually flew, the cost in the end was US$1.64 billion per Space Shuttle launch, including development.

NASA associate administrator William H. Gerstenmaier said in 2017 that there would be no official per flight cost estimates of any variety provided by NASA for SLS. Other bodies, such as the Government Accountability Office (GAO), the NASA Office of Inspector General, the Senate Appropriations Committee, and the White House Office of Management and Budget have put out cost per launch figures, however.

Several internal NASA programs and project concept study reports have released proposed budgets that include future SLS launches. For example, a concept study report for a space telescope was advised by NASA HQ in 2019 to budget US$500 million for an SLS launch in 2035. Another study in 2019 also proposing a space telescope assumed a budget for their launch of US$650 million in current day dollars, or US$925 million for when the launch would occur, which is also in the "mid-2030s".

Europa Clipper is a NASA scientific mission that was required by Congress to launch on the SLS. Oversight bodies both internal and external to NASA disagreed with this requirement. First, NASA's Inspector General office published a report in May 2019 that stated Europa Clipper would need to give up US$876 million for the "marginal cost" of its SLS launch. Then, an addendum to the letter published in August 2019 increased the estimate and stated that switching to a commercial rocket would actually save over US$1 billion. (Although this savings may have included a portion of costs related to the delay in launch schedule; a commercial alternative could launch sooner than SLS) A JCL (Joint Cost and Schedule Confidence Level) analysis cited in that letter put the cost savings at US$700 million, with SLS at US$1.05 billion per launch and the commercial alternative at US$350 million.

Finally, a letter from the White House Office of Management and Budget (OMB) to the Senate Appropriations Committee in October 2019 revealed that SLS's total cost to the taxpayer was estimated at "over US$2 billion" per launch after development is complete (program development has cost US$20 billion to date in 2020 dollars). The letter urged Congress to remove this requirement, in agreement with the NASA Inspector General, adding that using a commercial launch vehicle for Europa Clipper instead of SLS would save US$1.5 billion overall. NASA did not deny this US$2 billion cost of launch and an agency spokesperson stated it "is working to bring down the cost of a single SLS launch in a given year as the agency continues negotiations with Boeing on the long-term production contract and efforts to finalize contracts and costs for other elements of the rocket". This OMB figure is dependent on the rate of construction, so building more SLS rockets faster could decrease the per-unit cost. For example, Exploration Ground Systems – whose only role is to support, assemble, integrate, and launch SLS – has separately budgeted fixed costs of US$600 million per year on facilities, spread across however many rockets launch that year. Then NASA Administrator Jim Bridenstine shared informally that he disagrees with the US$2 billion figure since the marginal cost of an SLS launch should decrease after the first few, and is expected to end up around US$800 million to US$900 million, although contract negotiations were only just beginning for those later cores.

On 1 May 2020, NASA awarded a contract extension to Aerojet Rocketdyne to manufacture 18 additional RS-25 engines with associated services for US$1.79 billion, bringing the total RS-25 contract value to almost US$3.5 billion.

Constellation

From 2009 to 2011, three full-duration static fire tests of five-segment SRBs were conducted under the Constellation Program, including tests at low and high core temperatures, to validate performance at extreme temperatures. The 5-segment SRB would be carried over to SLS.

Early SLS

Engineers with Exploration Ground Systems and Jacobs prepare to lift and place the core stage of the Space Launch System rocket for the Artemis I mission on the mobile launcher and in-between the already assembled twin rocket boosters.

During the early development of the SLS a number of configurations were considered, including a Block 0 variant with three main engines, a Block 1A variant with upgraded boosters instead of the improved second stage, and a Block 2 with five main engines and the Earth Departure Stage, with up to three J-2X engines. In February 2015, it was determined that these concepts would exceed the congressionally mandated Block 1 and Block 1B baseline payloads.

On 14 September 2011, NASA announced the new launch system, which is intended to take the agency's astronauts farther into space than ever before and provide the cornerstone for future U.S. human space exploration efforts in combination with the Orion spacecraft.

On 31 July 2013, the SLS passed the Preliminary Design Review (PDR). The review included not only the rocket and boosters but also ground support and logistical arrangements. On 7 August 2014, the SLS Block 1 passed a milestone known as Key Decision Point C and entered full-scale development, with an estimated launch date of November 2018.

In 2013, NASA and Boeing analyzed the performance of several EUS engine options. The analysis was based on a second-stage usable propellant load of 105 metric tons, and compared stages with four RL10 engines, two MARC-60 engines, or one J-2X engine.

In 2014, NASA also considered using the European Vinci instead of the RL10. The Vinci offers the same specific impulse but with 64% greater thrust, which would allow for the same performance at lower cost.

Northrop Grumman Innovation Systems has completed full-duration static fire tests of the five-segment SRBs. Qualification Motor 1 (QM-1) was tested on 10 March 2015. Qualification Motor 2 (QM-2) was successfully tested on 28 June 2016.

SLS History

Artemis I core stage going into the Vehicle Assembly Building

As of 2020, three SLS versions are planned: Block 1, Block 1B, and Block 2. Each will use the same core stage with four main engines, but Block 1B will feature the Exploration Upper Stage (EUS), and Block 2 will combine the EUS with upgraded boosters.

In mid-November 2014, construction of the first core stage hardware began using a new welding system in the South Vertical Assembly Building at NASA's Michoud Assembly Facility. Between 2015 and 2017, NASA test fired RS-25 engines in preparation for use on SLS.

As of late 2015, the SLS program was stated to have a 70% confidence level for the first crewed Orion flight by 2023, and as of 2020, NASA is continuing to project a 2023 launch.

A test article build for the core stage began on 5 January 2016 and was expected to be completed in late January 2016. Once completed the test article was to be sent to ensure structural integrity at Marshall Space Flight Center. A structural test article of the ICPS was delivered in 2015. the core stage for Artemis 1 completed assembly in November 2019.

The first core stage left Michoud for comprehensive testing at Stennis in January 2020. The static firing test program at Stennis Space Center, known as the Green Run, will operate all the core stage systems simultaneously for the first time. Test 7 (of 8), the wet dress rehearsal, was carried out in December 2020 and the hot fire (test 8) took place on 16 January 2021, but shut down earlier than expected, about 67 seconds in total rather than the desired eight minutes. The reason for the early shutdown was later reported to be because of conservative test commit criteria on the thrust vector control system, specific only for ground testing and not for flight. If this scenario occurred during a flight, the rocket would have continued to fly normally. There was no sign of damage to the core stage or the engines, contrary to initial concerns. The second hot fire test was successfully completed March 18, with all 4 engines igniting, throttling down as expected to simulate in-flight conditions, and gimballing profiles. The core stage was shipped down to Kennedy Space Center to be mated with the rest of the rocket for Artemis 1. It left Stennis on April 24, and arrived at Kennedy on April 27. It was refurbished there in preparation for stacking. On 12 June 2021, NASA announced the assembly of the first SLS rocket was completed at the Kennedy Space Center. The assembled SLS is planned to be used for the unmanned Artemis 1 mission later in 2021.

The intended uncrewed first flight of SLS has slipped multiple times: originally from late 2016  to October 2017, then to November 2018, then to 2019, then to June 2020, then to April 2021, and most recently to November 2021.

Criticism

NASA moved out US$889 million of costs relating to SLS boosters, but did not update the SLS budget to match, a March 2020 Inspector General report found. This kept the budget overrun to 15% by FY 2019. At 30%, NASA would have to notify Congress and stop funding unless Congress reapproves and provides additional funding. The Inspector General report found that were it not for this "masking" of cost, the overrun would be 33% by FY 2019. The GAO separately stated "NASA's current approach for reporting cost growth misrepresents the cost performance of the program".

The SLS has been criticized on the basis of program cost, lack of commercial involvement, and the non-competitive nature of a vehicle legislated to use Space Shuttle components.

In 2009, the Augustine commission proposed a commercial 75 t (74 long tons; 83 short tons) launcher with lower operating costs, and noted that a 40–60 t (39–59 long tons; 44–66 short tons) launcher was the minimum required to support lunar exploration.

In 2011–2012, the Space Access Society, Space Frontier Foundation and The Planetary Society called for the cancellation of the project, arguing that SLS will consume the funds for other projects from the NASA budget. U.S. Representative Dana Rohrabacher and others proposed that an orbital propellant depot should be developed and the Commercial Crew Development program accelerated instead. A NASA study that was not publicly released and another from the Georgia Institute of Technology showed this option to be possibly cheaper. In 2012, the United Launch Alliance also suggested using existing rockets with on-orbit assembly and propellant depots as needed. The lack of competition in the SLS design was highlighted. In the summer of 2019, a former ULA employee claimed that Boeing, NASA's prime contractor for SLS, viewed orbital refueling technology as a threat to SLS and blocked further investment in it.

In 2011, Mars Society/Mars Direct founder Robert Zubrin suggested that a heavy lift vehicle could be developed for US$5 billion on fixed-price requests for proposal.

In 2010, SpaceX's CEO Elon Musk claimed that his company could build a launch vehicle in the 140- to 150-tonne payload range for US$2.5 billion, or US$300 million (in 2010 dollars) per launch, not including a potential upper-stage upgrade. In the early 2010s, SpaceX went on to start development of SpaceX Starship, a planned fully reusable super-heavy launch system. Reusability is claimed to allow the lowest-cost super-heavy launcher ever made. If the price per launch and payload capabilities for the Starship are anywhere near Musk's claimed capabilities, the rocket will be substantially cheaper than the SLS.

In 2011, Rep. Tom McClintock and other groups called on the Government Accountability Office (GAO) to investigate possible violations of the Competition in Contracting Act (CICA), arguing that Congressional mandates forcing NASA to use Space Shuttle components for SLS are de facto non-competitive, single source requirements assuring contracts to existing Shuttle suppliers. The Competitive Space Task Force, in September 2011, said that the new government launcher directly violates NASA's charter, the Space Act, and the 1998 Commercial Space Act requirements for NASA to pursue the "fullest possible engagement of commercial providers" and to "seek and encourage, to the maximum extent possible, the fullest commercial use of space". Opponents of the heavy launch vehicle have critically used the name "Senate launch system", a name that was still being used by opponents to criticize the program in 2021, as "the NASA Inspector General said the total cost of the rocket would reach $27 billion through 2025."

In 2013, Chris Kraft, the NASA mission control leader from the Apollo era, expressed his criticism of the system as well. Lori Garver, former NASA Deputy Administrator, has called for canceling the launch vehicle alongside the Mars 2020 rover. Phil Plait has voiced his criticism of SLS in light of ongoing budget tradeoffs between the Commercial Crew Development and SLS budgets, also referring to earlier critiques by Garver.

In 2019, the Government Accountability Office found that NASA had awarded Boeing over US$200 million for service with ratings of good to excellent despite cost overruns and delays. As of 2019, the maiden launch of SLS was expected in 2021. NASA continued to expect that the first orbital launch would be in 2021 as late as May 2020.

On 1 May 2020, NASA awarded a US$1.79 billion contract extension for the manufacture of 18 additional RS-25 engines. Ars Technica, in an article published on the same day, highlighted that over the entire RS-25 contract the price of each engine works out to US$146 million and that the total price for the four expendable engines used in each SLS launch will be more than US$580 million. They critically commented that for the cost of just one engine, six more powerful RD-180 engines could be purchased, or nearly an entire Falcon Heavy launch with two thirds of the SLS lift capacity.

Former NASA Administrator Charlie Bolden, who oversaw the initial design and development of the SLS, also voiced his criticism of the program in an interview with Politico in September 2020. Bolden said that the "SLS will go away because at some point commercial entities are going to catch up". Bolden further stated "commercial entities are really going to build a heavy-lift launch vehicle sort of like SLS that they will be able to fly for a much cheaper price than NASA can do SLS".

Penny4NASA

From Wikipedia, the free encyclopedia
 
Penny4NASA
Penny4NASA Logo
Formation2012
FoundersJohn Zeller,
Evan Schurr
PurposeSpace advocacy
Executive Director
John Zeller
Social Media
Curtiss Thompson
Video Development
Evan Schurr
Web Development
Joseph Spens
John Zeller,
Trevor Waddell,
Kyle Sullivan,
Nick Saab,
Evan Schurr
Parent organization
Space Advocates

Penny4NASA is a campaign run by the Space Advocates nonprofit, a nonpartisan organization seeking to promote the expansion of funding for the economic, scientific and cultural value of the United States' national space program by advocating an increase in the budget for the National Aeronautics and Space Administration to at least one percent of the United States Federal Budget. Penny4NASA also attempts to promote public awareness of the NASA mission and budget, and has produced a series of outreach videos, as well as performing educational outreach via social media.

Overview

Penny4NASA is a campaign of Space Advocates, an initiative founded by John Zeller in 2012, and proposes an increase in the budget for the National Aeronautics and Space Administration to promote the scientific and technological goals of the space agency. The organization works to accomplish these aims through public outreach, educational materials, and has organized petitions to the Executive and Legislative branches of the United States government toward those aims. Penny4NASA is the campaign Space Advocates is best known for.

The Penny4NASA campaign was founded in 2012 following the testimony of astrophysicist Neil DeGrasse Tyson – curator of the Hayden Planetarium in New York – before the United States Senate Science Committee. According to Tyson's testimony, “Right now, NASA’s annual budget is half a penny on your tax dollar. For twice that—a penny on a dollar—we can transform the country from a sullen, dispirited nation, weary of economic struggle, to one where it has reclaimed its 20th century birthright to dream of tomorrow.”

Objectives

The Penny4NASA mission statement declares that a main goal of the campaign is to call upon the White House and U.S. Congress "to increase NASA's funding from its current level of 0.48% to a whole one percent of the US annual budget." The organization hopes to meet this aim by encouraging to public to "consistently and in large numbers, [contact] members of congress to tell them what [the public] want[s]."

Another goal of the Penny4NASA campaign, as part of its larger goal to influence the public in favor of increasing the funding allotted the U.S. space program, is to communicate accurate information about how much funding has been allotted NASA over its operational history. The mission statement states that "2012 is the 2nd lowest year of NASA funding by percentage of the US budget since 1958 and 1959, their founding years."

Neil deGrasse Tyson, a stated influence of the Penny4NASA organization, has argued that NASA is not only underfunded, but that the general public overestimates how much revenue is allocated to the space program. At a March 2010 talk delivered in the University at Buffalo's Distinguished Speaker series, Tyson stated:

"By the way, how much does NASA cost? It's a half a penny on the dollar. Did you know that? The people are saying, 'Why are we spending money […].' I ask them, 'How much do you think we're spending?' They say 'five cents, ten cents on a dollar.' It's a half a penny."

Tyson has proposed increasing the budget of NASA and suggested that doing so would increase the capabilities of human spaceflight, allowing the space program to "do it all," referring to pursuing multiple avenues of exploration.

Media coverage and reception

In March 2012, Neil deGrasse Tyson was interviewed by Joshua Topolsky. Speaking of the Penny4NASA campaign and social media initiatives, Tyson said he was surprised by the online mobilization within 10 days of his Senate committee testimony, and that he was "happy to learn that" people were moved by it.

On June 10, 2012 John Zeller, then an undergraduate student at Oregon State University majoring in Computer Science, was interviewed in the Science for the People podcast. Zeller started the Penny4NASA.org web site after observing Neil deGrasse Tyson giving a testimony before the U.S. Senate committee on Commerce, Science, and Transportation. Zeller states, "After watching this video, I went on Twitter and Facebook and I saw hashtag Penny4NASA all over the place. There had been a video put on YouTube that had hashtag Penny4NASA all over it that was trending around 300,000 views." The success of the video prompted Zeller to begin the web site and set up a petition and social media around the 'Penny4NASA' hashtag that had come to summarize the proposal of its movement.

A September 2, 2012 episode of Astronomy Cast recorded at DragonCon in Atlanta, Georgia focused on funding issues related to space exploration. Discussing the Penny4NASA proposal and supportive of its goals, astronomer Pamela Gay stated that it may not be a realistic goal to "convince the Congress to take a penny of every tax dollar and give it to NASA," but went on to say it may be possible to produce "the same ultimate effect by individuals who have the extra ten dollars and care about science and finding that science project that they believe in and giving it ten dollars."

Campaign efforts

In 2012, Penny4NASA organization released a two-part video series titled "We Stopped Dreaming" to make a case for expanding the combined efforts of the National Aeronautics and Space Administration, international space partnerships, private space exploration and combinations thereof. Two additional videos by Brandon Fibbs were subsequently released in 2012, "Dare Mighty Things: Curiosity on Mars" and "Audacious Visions."

A petition was created in March 2012 on behalf of Penny4NASA using the U.S. White House's We the People petitioning system. The petition argued for a reallocation of funding, stating that the investment would be smaller than recent government expenditures, including the Troubled Asset Relief Program during the financial crisis of 2007–2008. The White House issued an official response to the initial petition, entitled Doubling and Tripling What We Can Accomplish in Space, stating "NASA and space are so important to our future that we do need to be doubling and tripling what we can accomplish in this domain." The White House's response also emphasized fiscal challenges but argued that through effective spending to deliver results, "NASA is as strong as ever."

On August 9, 2012, Penny4NASA published a response in an open letter to White House Office of Science and Technology Policy Director John Holdren, acknowledging fiscal challenges, but adding that they were "concerned that the message of [the] organization and the almost 30,000 individuals who have signed the petition is being overlooked."

As of January 2013, the petition was taken down from the We the People website for not meeting the signature threshold.

Following the White House petition, the Penny4NASA organization endorsed a congressional petition using the POPVOX widget, an online tool for communicating support or dissent for particular bills on behalf of its user base to the members of the United States Congress in a public forum.

Lie point symmetry

From Wikipedia, the free encyclopedia https://en.wikipedia.org/wiki/Lie_point_symmetry     ...